BPAs and the Law
Once again, Blanket Purchase Agreements (BPAs) are simplified
contract vehicles allowing agencies to fill repetitive orders
for commercial, off-the-shelf goods and services. BPAs have become
a very popular procurement vehicle, especially GSA BPAs, which
are BPAs placed under a vendors GSA Schedule Contract. This
is because there is no limit on the dollar value of individual
task or delivery orders or requirement to publicize orders placed
under a GSA Schedule BPA.
So what is the law governing BPAs? What regulations govern an
agency awarding a BPA or multiple BPAs? What policies apply to
an agency placing an order under a GSA Schedule BPA?
Establishing BPAs: Federal Acquisition Regulation (FAR)
§ 13.303-1 says that an agency may establish a BPA with a
single company for repetitive orders, or with multiple companies
to provide maximum practicable competition, or with GSA Schedule
contractors. However, the FAR does not state exactly how an agency
should go about selecting BPA contractors. It is simply a matter
of identifying vendors and negotiating with them.
When it comes to awarding a GSA Schedule BPA, GSA has stated that
any agency must follow FAR 8.404 before awarding a GSA Schedule
BPA. That regulation requires an agency to review the pricelists
of three or more GSA Schedule contractors before making a best
value selection.
The Air Force takes a more formal approach and recommends that
an ordering activity publicize in the Commerce Business Daily
or on its electronic bulletin board its intent to award one or
more GSA Schedule BPAs. (http://safaq.hq.af.mil/contracting/affars/98-c-07.htm).
The Air Force also recommends that the ordering activity outline
the evaluation/selection criteria and provide instructions on
how to respond to the invitation.
The General Accounting Offices decisions on the establishment
of BPAs are unclear. For plain vanilla BPAs awarded under FAR
Part 13, Simplified Acquisition Procedures, the GAO has stated
that agencies are not required to request proposals or to conduct
a competition when establishing a single BPA or multiple BPAs.
Information Systems Technology Corp., B-280013, Aug. 6, 1998,
98-2 CPD ¶ 36. That rule, however, would appear to apply
only to plain vanilla BPAs awarded under FAR Part 13, Simplified
Acquisition Procedures, and would not apply to GSA Schedule BPAs
awarded under FAR 8.404. The Information Systems Technology case,
however, clearly involved GSA Schedule BPAs, making the GAOs
holding inconsistent.
The GAO is clear that if an agency conducts a competition, then
the agency must treat all contractors fairly and equally. In the
Information Systems Technology case, a contractor complained that
the agency had incorrectly evaluated the technical merit of its
offer submitted in response to the agencys notice that it
wanted to establish multiple BPAs. The GAO reviewed the agencys
technical evaluation to confirm that it rationally supported the
agencys finding that the protesters offer was technically
inferior.
The Information Systems Technology case also shows that an agency
can award BPAs based on the technical merit of contractors, even
if higher priced than other vendors. At the opposite end of the
best value spectrum, the GAO has also sustained an agency action
that awarded BPAs on the basis of best price where the agency
found the offerors products essentially equivalent. Pfizer,
Inc., B-276362, June 6, 1997, 97-1 CPD ¶ 205.
Awarding Orders Under BPAs: FAR § 13.303-5(d) states
that if there are an insufficient number of BPAs to insure maximum
practicable competition for BPA orders over the $2,500 micro-purchase
threshold, then the agency should either solicit from other sources
or seek to establish additional BPAs.
GSAs approach to placing orders under GSA Schedule BPAs
is much less restrictive than the FAR. GSAs Multiple Award
Schedule Virtual Campus (http://pub.fss.gsa.gov/schedules/building3.cfm)
specifically states that once a BPA has been awarded, purchase
orders can be placed without further competition, documentation,
or justification. The reasoning behind GSAs position is
that the agency was required to follow the competition requirements
of FAR § 8.404 when establishing the GSA Schedule BPA.
In my opinion, GSAs interpretation of FAR § 13.303-5(d)
is wrong. Even after a GSA Schedule BPA is awarded, an agency
should still comply with the requirements of FAR § 8.404
before awarding orders. This is consistent with a footnote in
the GAOs Information Systems Technology decision, in which
the GAO noted that applicable competition requirements still apply
to all purchases under a BPA after it is awarded.
The Air Force takes a narrower course more in keeping with FAR
§ 13.303-5(d) and the Information Systems Technology case
by requiring its ordering activities to comply with FAR §
8.404 when placing orders (http://safaq.hq.af.mil/contracting/affars/98-c-07.htm).
The Air Force goes on to recommend a structured evaluation process
requiring the submission of the information the activity needs
to make a proper best value award.
The GAO, while giving agencies wide latitude when placing BPA
orders, still requires agencies to treat contractors fairly. In
Comark Federal Systems, B-278343, Jan. 20, 1998, 98-1 CPD ¶
34, the agency issued a Request for Quotations (RFQ) to several
GSA IT Schedule BPA contractors. The RFQ called on the Schedule
vendors to select, from among the numerous possible configurations
of the items on their Schedules, a particular configuration on
which to submit a quotation. The agency conducted a detailed technical
evaluation and cost/technical trade-off determination on the vendors
responses to the RFQ.
The GAO ruled that the RFQ went beyond the bounds of a simple
best buy into the realm of a negotiated procurement. The agencys
RFQ, as drafted, shifted the responsibility for selecting items
from the agency to the vendors. The agencys detailed technical
evaluation and cost/technical trade-off determination also amounted
to a negotiated procurement under FAR Part 15.
So there you have it. As much as we would all like clear cut,
indisputable rules to follow, the law governing the establishment
of BPAs and placement of orders under both plain and GSA Schedule
BPAs is unsettled. Considering the increasing popularity of these
procurement vehicles, the rules will continue to be refined over
the next several years.