What GAO is Saying About Schedule Orders
I recently described in this column the rules governing the placement
of GSA Schedule orders under the Federal Acquisition Regulations
(FAR) Subpart 8.4 (Placing GSA Schedule Orders). To recap, when
an agency orders goods or services from a GSA Schedule contractor,
FAR § 8.404 requires an agency to place the order with the
Schedule contractor whose product represents the best value
and meets the agencys needs at the lowest overall cost.
In this months installment, I discuss the lessons to be
learned from recent General Accounting Office (GAO) procurement
decisions interpreting those FAR rules.
To begin with, the GAO has consistently denied most contractor
protests against an agencys placement of a GSA Schedule
order. The GAOs standard in these cases is whether the agencys
issuance of the Schedule order was reasonable. In particular,
the question the GAO asks in reviewing such cases is not whether
the agency action was the most reasonable course of action it
could have taken, but whether there is any reasonable basis for
the decision. Therefore, in the case of GSA Schedule contracts,
GAO asks whether the agencys best value determination was
at all reasonable.
If an agency, for example, places an order against a federal supply
schedule contract at a price higher than that offered by another,
the GAO will deny the protest if the record shows that the agency
reasonably concluded that the ordered product is the lowest price
schedule item meeting the agencys actual needs. CPAD Technologies,
Inc., B-278582, Feb. 19, 1998, 98-1 CPD ¶ 55. The determination
of the agencys needs and which product meets those needs
is considered by the GAO to be the agencys responsibility.
In CPAD the GAO has deemed reasonable an agencys selection
of a detection system when it considered the systems lighter
weight, smaller size, and effectiveness of operation over a competitors
in its decision.
The GAO has also considered reasonable an agencys purchase
of medical devices through a delivery order placed under a GSA
Schedule contract when the agency took into account warranty conditions
and special safety features considered essential to meet the agencys
needs. Midmark Corporation, B-278298, Jan. 14, 1998, 98-1 CPD
¶ 17. In this situation, the GAO found that the agency reasonably
determined that the awardees device met agency requirements
and that the competitors product did not. Furthermore, the
GAO ruled that the losing vendors assertions that it could
have provided the same safety features and offered the same warranty
as the chosen vendor, at an unspecified price, did not establish
that the model would meet the agencys requirements at the
lowest price.
In Midmark, the GAO also stated that there is no requirement under
the regulations governing the use of the GSA Schedules that vendors
holding GSA Schedule contracts be provided with an exact statement
of the agencys needs or that agencies negotiate special
terms or conditions with GSA Schedule contractors for individual
purchases. Such a requirement, the GAO feels, would be inconsistent
with the catalog-type approach of the GSA Schedule program.
Although the GAO gives agencies wide latitude and much deference
when reviewing the reasonableness of procurement decisions, there
are limits. In Comark Federal Systems, B-278343, Jan. 20, 1998,
98-1 CPD ¶ 34, the agency issued a Request for Quotations
(RFQ) to several GSA Schedule contractors that had been issued
Blanket Purchase Agreements for information technology products.
The RFQ called on the Schedule vendors to select, from among the
numerous possible configurations of the items on their Schedules,
a particular configuration on which to submit a quotation. The
agency later conducted a detailed technical evaluation and cost/technical
trade-off determination on the vendors responses to the RFQ.
The GAO ruled the RFQ went beyond the bounds of a simple best
buy into the realm of a negotiated procurement. The agencys
RFQ, as drafted, shifted the responsibility for selecting items
from the agency to the vendors. The agencys detailed technical
evaluation and cost/technical trade-off determination also amounted
to a negotiated procurement under FAR Part 15.
Therefore, if an agency intends to use the vendors responses
as the basis of a detailed technical evaluation and cost/technical
trade-off, the agency has elected to use an approach that is more
like a competition in a negotiated procurement than a simple GSA
Schedule best buy. In such a situation, the RFQ must
provide for a fair and equitable competition, including advance
notice regarding the agencys needs and selection criteria.
However, an agencys issuance of an RFQ merely to solicit
final pricing or price reductions from competing GSA Schedule
contractors does not amount to a negotiated procurement. CPAD.
Considering the important role that GSA Schedules now play in
the federal procurement process, current and prospective GSA Schedule
vendors must understand the rules of the game and how the GAO
is interpreting those rules in order to take advantage of hundreds
of millions of dollars a year in GSA Schedule business opportunities.
Note: Recent decisions from the GAO are available on the web
at www.gao.gov
under the heading Comptroller General Decisions and Opinions.